Civil Engineers’ Corner

Road work will occur in the Ramstein housing area this week.
• Phase I – Georgia Street from Alabama Boulevard to Virginia Boulevard continuing with Virginia Boulevard
• Phase II – Kansas Street from Virginia Boulevard to Michigan Boulevard
• 7:30 a.m. to 6 p.m. Monday
The top asphalt layer on roads will be scraped off for both phases. Cars must remain in parking lots but can drive on the road during this time. Cars can not be parked on the street.
• 8 a.m. to 6 p.m Tuesday
Phase I – Paving
After 8 a.m., cars can not be parked on street. Road will be opened for use by 6 p.m.
• 8 a.m. to 6 p.m. Wednesday
Phase II – Paving
After 8 a.m., cars can not be parked on street. Road will be opened for use by 6 p.m.